009-1999 GYH Install Runway Vertical/Visual Guidance System $367,245 $0 $367,245
009-1999 GYH Install Runway Lighting $379,577 $0 $379,577
010-1999 GYH Conduct Airport Master Plan Study $77,850 $0 $77,850
GYH Fiscal Year total for 1999 $931,187 $0 $931,187
008-1996 GYH Rehabilitate Runway $0 $390,000 $390,000
007-1996 GYH Rehabilitate Runway $600,000 $0 $600,000
GYH Fiscal Year total for 1996 $600,000 $390,000 $990,000
006-1995 GYH Install Guidance Signs $0 $58,500 $58,500
GYH Fiscal Year total for 1995 $0 $58,500 $58,500
005-1994 GYH Rehabilitate Taxiway $447,153 $11,529 $458,682
GYH Fiscal Year total for 1994 $447,153 $11,529 $458,682
004-1991 GYH Rehabilitate Runway $5,829 $294,171 $300,000
004-1991 GYH Extend Runway $0 $45,000 $45,000
GYH Fiscal Year total for 1991 $5,829 $339,171 $345,000
003-1990 GYH Install Runway Vertical/Visual Guidance System $51,575 $0 $51,575
003-1990 GYH Install Apron Lighting $143,496 $0 $143,496
GYH Fiscal Year total for 1990 $195,071 $0 $195,071
001-1985 GYH Conduct Miscellaneous Study $0 $34,506 $34,506
002-1985 GYH Install Miscellaneous NAVAIDS $0 $8,000 $8,000
002-1985 GYH Extend Runway $0 $35,000 $35,000
GYH Fiscal Year total for 1985 $0 $77,506 $77,506
GYH Airport Summary all years $4,131,842 $3,942,618 $8,074,460
0013-018-2012-2012 JZI Update Airport Master Plan Study [Master Plan Update] $61,798 $0 $61,798
JZI Fiscal Year Total for 2012 $61,798 $0 $61,798
017-2011-2011 JZI Acquire Land For Approaches $216,321 $0 $216,321
JZI Fiscal Year Total for 2011 $216,321 $0 $216,321
016-2009 JZI Expand Apron $0 $1,583,760 $1,583,760
015-2009 JZI Rehabilitate Runway $131,154 $4,886,849 $5,018,003
014-2009 JZI Rehabilitate Runway $2,254,378 $0 $2,254,378
JZI Fiscal Year total for 2009 $2,385,532 $6,470,609 $8,856,141
012-2008 JZI Rehabilitate Taxiway $2,539,035 $0 $2,539,035
013-2008 JZI Rehabilitate Runway $208,864 $0 $208,864
012-2008 JZI Rehabilitate Runway $662,810 $0 $662,810
JZI Fiscal Year total for 2008 $3,410,709 $0 $3,410,709
011-2007 JZI Conduct Airport Master Plan Study $50,000 $0 $50,000
011-2007 JZI Expand Apron $3,056,316 $0 $3,056,316
011-2007 JZI Rehabilitate Taxiway $31,000 $0 $31,000
011-2007 JZI Improve Runway Safety Area $50,000 $0 $50,000
JZI Fiscal Year total for 2007 $3,187,316 $0 $3,187,316
010-2005 JZI Rehabilitate Runway $1,173,250 $0 $1,173,250
010-2005 JZI Rehabilitate Taxiway $1,121,773 $0 $1,121,773
010-2005 JZI Expand Apron $800,000 $0 $800,000
JZI Fiscal Year total for 2005 $3,095,023 $0 $3,095,023
009-2002 JZI Install Weather Reporting Equipment $155,250 $0 $155,250
JZI Fiscal Year total for 2002 $155,250 $0 $155,250
008-2000 JZI Remove Obstructions $687,803 $0 $687,803
JZI Fiscal Year total for 2000 $687,803 $0 $687,803
007-1999 JZI Install Runway Lighting $575,309 $0 $575,309
007-1999 JZI Install Taxiway Lighting $148,969 $0 $148,969
JZI Fiscal Year total for 1999 $724,278 $0 $724,278
                  10   11   12   13   14   15   16   17   18   19   20   21   22   23   24   25   26   27   28   29   30   31   32   33   34   35   36   37   38   39   40   41   42   43   44   45   46   47   48   49   50  
2553 Airport Blvd., West Columbia, South Carolina 29170-2142    
(803) 896-6260 or (800) 922-0574
A-Z IndexEventsContact
FacebookFTP AccessAutodesk Express ViewerTHIS SITE IS BEST VIEWED IN 1024x768
THIS SITE REQUIRES IE7.0 OR HIGHER
THIS SITE REQUIRES PLUG-IN (click on the icon on the right to download)
Site Developed by USC Web Services Group
© 2011, SC Aeronautics. All Rights Reserved.