026-2002 CAE Security Enhancements $117,774 $75,780 $193,554
CAE Fiscal Year total for 2002 $117,774 $662,005 $779,779
024-2001 CAE Expand Apron $4,171,892 $0 $4,171,892
024-2001 CAE Install Runway Vertical/Visual Guidance System $0 $18,000 $18,000
024-2001 CAE Conduct Noise Compatibility Plan Study $27,000 $222,581 $249,581
024-2001 CAE Install Runway Lighting $349,002 $0 $349,002
023-2001 CAE Conduct Miscellaneous Study $71,413 $0 $71,413
024-2001 CAE Rehabilitate Taxiway $5,225,275 $0 $5,225,275
CAE Fiscal Year total for 2001 $9,844,582 $240,581 $10,085,163
022-2000 CAE Install Runway Vertical/Visual Guidance System $77,729 $0 $77,729
022-2000 CAE Expand Apron $237,386 $0 $237,386
022-2000 CAE Acquire Handicap Passenger Lift Device $34,196 $0 $34,196
022-2000 CAE Improve Runway Safety Area $1,666,963 $0 $1,666,963
022-2000 CAE Rehabilitate Taxiway $323,676 $0 $323,676
022-2000 CAE Install Runway Lighting $19,170 $0 $19,170
CAE Fiscal Year total for 2000 $2,359,120 $0 $2,359,120
020-1999 CAE Extend Runway $88,390 $0 $88,390
020-1999 CAE Improve Runway Safety Area $141,711 $0 $141,711
021-1999 CAE Extend Runway $315,824 $0 $315,824
020-1999 CAE Acquire Aircraft Rescue & Fire Fighting Vehicle $407,372 $0 $407,372
021-1999 CAE Acquire Snow Removal Equipment $267,624 $0 $267,624
020-1999 CAE Conduct Airport Master Plan Study $540,021 $0 $540,021
020-1999 CAE Expand Apron $119,673 $0 $119,673
CAE Fiscal Year total for 1999 $1,880,615 $0 $1,880,615
019-1998 CAE Acquire Security Equipment $125,448 $0 $125,448
CAE Fiscal Year total for 1998 $125,448 $0 $125,448
018-1997 CAE Install Miscellaneous NAVAIDS $210,920 $0 $210,920
018-1997 CAE Rehabilitate Runway Lighting $248,100 $0 $248,100
018-1997 CAE Extend Runway $1,544,151 $0 $1,544,151
018-1997 CAE Construct Taxiway $64,251 $0 $64,251
CAE Fiscal Year total for 1997 $2,067,422 $0 $2,067,422
017-1996 CAE Install Runway Lighting $0 $49,500 $49,500
017-1996 CAE Rehabilitate Runway $0 $3,393,500 $3,393,500
CAE Fiscal Year total for 1996 $0 $3,443,000 $3,443,000
015-1995 CAE Acquire Security Equipment $0 $149,850 $149,850
016-1995 CAE Construct Apron $0 $6,940,244 $6,940,244
015-1995 CAE Extend Runway $2,864,303 $695,960 $3,560,263
015-1995 CAE Construct Apron $1,729,146 $10,000,000 $11,729,146
CAE Fiscal Year total for 1995 $4,593,449 $17,786,054 $22,379,503
014-1993 CAE Install Guidance Signs $169,766 $262,058 $431,824
014-1993 CAE Improve Terminal Building $3,537,610 $0 $3,537,610
CAE Fiscal Year total for 1993 $3,707,376 $262,058 $3,969,434
013-1992 CAE Acquire Aircraft Rescue & Fire Fighting Safety Equipment $21,157 $0 $21,157
013-1992 CAE Improve Aircraft Rescue & Fire Fighting Building $523,440 $15,352 $538,792
013-1992 CAE Acquire Aircraft Rescue & Fire Fighting Vehicle $100,999 $0 $100,999
CAE Fiscal Year total for 1992 $645,596 $15,352 $660,948
012-1991 CAE Acquire Security Equipment $1,173,177 $0 $1,173,177
CAE Fiscal Year total for 1991 $1,173,177 $0 $1,173,177
011-1990 CAE Groove Runway $59,464 $0 $59,464
CAE Fiscal Year total for 1990 $59,464 $0 $59,464
                  10   11   12   13   14   15   16   17   18   19   20   21   22   23   24   25   26   27   28   29   30   31   32   33   34   35   36   37   38   39   40   41   42   43   44   45   46   47   48   49   50   51   52   53   54   55   56  
2553 Airport Blvd., West Columbia, South Carolina 29170-2142    
(803) 896-6260
A-Z IndexEventsContact
FAA Requires sUAS (Drone) RegistrationFacebookFTP Accessrequest publicationsAirport Clue ToolTHIS SITE IS BEST VIEWED IN 1024x768
THIS SITE REQUIRES IE7.0 OR HIGHER
Site Developed by USC Web Services Group
© 2011, SC Aeronautics. All Rights Reserved.